Side-by-side timelines showing how virtual inspections compress schedules.
Here are real-world timeline comparisons for common Florida trades.
County: 3-7 day wait. Virtual: Same day. Saved: 3-7 days.
→ See our comparison page details
County: 10-17 days (two inspections). Virtual: 2 days. Saved: 8-15 days.
County: 5-14 day wait. PTO delayed. Virtual: Same day. PTO starts immediately. Saved: 5-14 days.
County: 3-5 day wait. Cascades across entire build. Virtual: Same day. Saved: 3-5 days plus cascade effect.
Direct: $150-500/day per stalled project. Opportunity: $1,500-8,000/day in revenue capacity. The compounding effect across your portfolio transforms your economics.